Project Details
PROJECT
SUPPLY AND INSTALL RIVERBANK RAIL & TROLLEY PUMP SYSTEM WITH SCREENED
RIVER HOPPER.
DESCRIPTION
Develop and establish a pump system to ensure that pumping infrastructure could be safety and
easily installed/removed for maintenance and also enhance operational reliability.
INDUSTRY SECTOR
Mining.
INFRASTRUCTURE
110kW Submersible Dewatering Pump
and trolley system connecting into river hopper
screening and SS strainer assembly/stand
rated winch assembly and SS cabling with winch table
plinth and electrical control box
power cable and lay flat riser to discharge pipework
Galvanised rail
Grid Mesh
990lb
Concrete
Extended
DETAILS
Existing river pump performance was compromised due to locational and environmental issues therefore an alternative method for river pump placement and retrieval addressing inherent problems was developed.
Preparation of site including clearing and levelling of embankment, excavation of river bed, concrete plinth was conducted by J.A.C. Pump Services along with supply and installation of all pumping infrastructure.
Careful pump selection was required to ensure system compatibility requirements were met and 85l/s of river water could be pumped into existing network of pipes and pumps.